The zinc-copper crushing and processing facility is to be located in New South Wales, Australia, at the former Woodlawn Mine site.
PUBLICITÉ
The Woodlawn project includes civil, structural, mechanical, piping and commissioning works for the mineral processing plant. Works will start this year.
CIMIC Group CEO, Adolfo Valderas added: “The contract for this zinc-copper crushing and processing facility is a further example of CIMIC Group’s strategy to expand through diversifying by commodity or geography. The contract enhances Sedgman’s position as a global mineral specialist with a balanced commodity portfolio.”
The Engineering, Procurement and Construction (EPC) contract signed with Heron Ressources Limited is estimated to yield around $107M to Sedgman over eighteen months.